Reliability through experience

Follow us on :

2010

Turn-key construction from greenfield of a bioethanol production plant

Customer

Biowanze s.a., – Wanze – Belgium

General contractor

De Smet Engineers & Contractors

Scope of works

Turn-key supply of a bioethanol production plant

Industrial operation

2010

Plant capacity

300,000 m³ per year of bioethanol

26 MW electricity + 160 TPH vapor

Processing units
  • Wheat preparation
  • Gluten production
  • Bioethanol production
Utilities
  • Raw water treatment
  • Process water production
  • Power plant with cogeneration
  • Compressed air production
  • Fire fighting system
  • Natural gas station
Auxiliaries
  • Wheat unloading : ship, train and truck
  • Wheat storage
  • Gluten storage and expedition
  • Chemicals and enzymes storages
  • Bioethanol storage and expedition
  • Laboratory
  • Control room